Clean Room Project (Turnkey & Part of the Machinery) Solid Dosage Part
1- Conceptual design (conceptual) design project, citing the cGMP protocols.
2- Review and approve design) GMP review (by experts and final approval authority and approval of a drug references.
3- Preparation of engineering design (engineering design) with technical and administrative details of all calculations and detailed technical drawings and Cost of equipment and materials required for the project (detail design).
4- Bidding and final approval by the employer.
5- Transport equipment and parts required for the project from China to the project site located in Gorgan.
6- Sign technicians and installation and start of construction of the project.
7- Full completion of the project after 68 working days.
Machinery:
1- Solid Dosage Production Process From Canaan Co.
Area: 1450 m2
Effective Date: 2008